Pengerukan Lumpur Saluran PHB Kencana Capai 70 Persen

Kencana Connecting Channel Dredging Work Targeted to Finish This Month

Dredging work on Kencana Connecting (PHB) Channel on Jalan Muria Dalam RT 06/02, Menteng Atas Urban Village, Setiabudi, South Jakarta which conducted since early January is targeted to be completed by the end of this month.

Its progress reaches 70 percent

Setiabudi Sub-district Water Resources (SDA) Sub-agency Unit Head, Yansori, dredging was carried out along 314 meters, from Jalan Putri RT 06/02, Pasar Manggis Urban Village until Jalan Warung Belek, RW 02 Menteng Atas Urban Village.

"Its progress reaches 70 percent. If it goes well, we are targeting it to finish by the end of March," he conveyed, Saturday (3/27).

PPSU Personnel Repair Drainage Cover on Jalan Duren Tiga

According to him, mud dredging work is carried out as deep as 30-100 centimeters. His side deployed 7 SDA Unit personnel and 1 excavator to dredge mud from the channel.

"Channel needs to be cleaned because the silt already dense thus it can't hold much water. After dredging, we hope it can increase its capacity," he stated.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye680 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye510 personAldi Geri Lumban Tobing
  3. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye506 personAldi Geri Lumban Tobing
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye481 personFakhrizal Fakhri
  5. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye471 personAnita Karyati